How Long Does a Kitchen Remodel Take in Virginia Beach?

Timeline, permits, and what to expect from start to finish

One of the first questions we hear from homeowners is simple:
How long will my kitchen remodel actually take?

The answer depends on the size of the project, material selections, and permitting requirements — but most kitchen remodels in Virginia Beach take 6 to 12 weeks once construction begins.

The key is understanding what happens during each phase, and where delays can occur.

Here’s a realistic timeline from a licensed Virginia Beach remodeling contractor.

Phase 1: Planning & Design (2–4 weeks)

Before demo starts, the layout, materials, and scope must be finalized.

This includes:

  • Cabinet selection

  • Appliance specifications

  • Layout adjustments

  • Electrical and plumbing planning

  • Ordering materials with long lead times

Cabinets are often the longest lead item. Depending on the manufacturer, lead times can range from 3 to 8 weeks, especially with custom options.

Planning properly prevents delays later.

Phase 2: Permits & Scheduling (1–3 weeks)

Most kitchen remodels in Virginia Beach require permits, especially if electrical, plumbing, or structural work is involved.

This ensures the work meets local building codes and safety standards.

Working with an experienced contractor helps streamline the approval process and avoid unnecessary delays.

Phase 3: Demolition (2–5 days)

This is when the visible transformation begins.

During demolition, we remove:

  • Cabinets

  • Countertops

  • Flooring

  • Fixtures

  • Drywall if needed

This phase moves quickly, but it sets the stage for everything that follows.

Phase 4: Rough-In Work (1–2 weeks)

This includes:

  • Electrical updates

  • Plumbing adjustments

  • Structural framing if needed

  • HVAC modifications

After rough-in work, required inspections must be completed before moving forward.

This ensures everything is safe, compliant, and built to last.

Phase 5: Installation (2–4 weeks)

This phase includes:

  • Cabinet installation

  • Countertops

  • Flooring

  • Tile backsplash

  • Lighting fixtures

  • Trim and finishing details

Cabinet installation is one of the most important milestones because everything else builds off of it.

Phase 6: Final Inspections & Completion (1 week)

Final inspections ensure all work meets Virginia Beach code requirements.

Once approved, final touch-ups and cleaning complete the project.

Your kitchen is ready to use.

What Can Affect Your Kitchen Remodel Timeline?

Several factors can influence how long your renovation takes:

  • Permit approval timelines

  • Custom cabinet lead times

  • Inspection scheduling

  • Coastal supply chain availability

  • Change orders during construction

In coastal areas like Virginia Beach, material delivery timelines can vary, especially during busy construction seasons.

Working with an experienced local contractor helps minimize these delays.

How Communication Keeps Projects on Track

One of the biggest causes of delays in kitchen remodels is lack of communication.

That’s why we use Buildertrend project management software to keep clients informed with:

  • Real-time updates

  • Daily progress logs

  • Scheduling visibility

  • Photo documentation

This ensures homeowners always know what’s happening — and what’s next.

No guessing. No surprises.

The Bottom Line

Most kitchen remodels in Virginia Beach take 6 to 12 weeks during construction, plus planning and permitting time beforehand.

The best way to ensure a smooth, efficient renovation is working with an experienced Virginia Beach remodeling contractor who understands local codes, scheduling, and material timelines.

At Tidewater Structures, we focus on clear communication, strong planning, and quality craftsmanship to deliver kitchens built to last.